Measuring cash flow and overdraft for fuzzy project networks with overlapping activities

oleh: Min-Chun Yu, Hui-Chung Yeh, Van-Loi Dang

Format: Article
Diterbitkan: Vilnius Gediminas Technical University 2017-04-01

Deskripsi

Overlapping activities with imprecise durations to accelerate schedules has an impact on scheduling a con­struction project. The project may need to be rescheduled to suit the available overdraft limitation rather than to adopt the least total cost schedule. However, past research has seldom conducted a risk analysis on the project cash flow and overdraft requirements for projects with overlapping activities in a fuzzy environment. This research uses fuzzy DSM-based scheduling and proposes an algorithm to calculate the cash flow and overdraft at different risk levels. A numerical example is illustrated to demonstrate the algorithm’s effectiveness.